Hi,

When I try to modify a task directly from Grantt Chart view I drag, say, finish day by my mouse. It moves and I can see all changes. However, if I reload the page or go to other page - all changes are gone.

The only way to make change for deadline or start/finish day is to go directly into the task, click Edit and make the changes.

Does anyone experience the similar problem? What should I do to fix it?

Thanks.
Hi Dmitry!

When you drag the task in Gantt view - it changes start & end date but not the deadline - the changed end date should stay after page reload, if you're experiencing any wrong program behaviour in this regard - please report it to our Helpdesk  asap. Thank you.

Best,

Yana.